Part 3: Public Works Contracts & Subcontractors: Prime Contracts Over $25,000

In reality, most public works projects are over $25,000.00 in value. When projects exceed $25,000.00 in value, the general contractor must post a payment bond in the amount of the prime contract for the protection of subcontractors and sub-subcontractors. Tex. Gov’t Code § 2253.021. If subcontractors are not paid by the general contractor, they can file a lawsuit to collect on the payment bond; however, before they can file suit, subcontractors must ensure that they have complied with strict notice requirements. If the notice requirements, including deadlines and content, are not properly met, the subcontractor will not be able to successfully sue to collect on the payment bond.

Subcontractors (those having a contract directly with the general contractor) must give written notice to the prime contractor and surety not later than the fifteenth day of the third month following each month in which the labor or material was provided for which the claimant has not been paid (often called the “Third Month Notice”). Tex. Gov’t Code § 2253.041(b). If this deadline is not properly met, the subcontractor will have lost its ability to prevail in a lawsuit. Furthermore, the notice must identify specific details such as: the labor or materials provided; who they were provided to; and when they were provided; in addition to other required information. Additionally, a sworn statement must be included verifying the amount due. Tex. Gov’t Code § 2253.041(c). The notices must be mailed by the proper method and to the proper addresses. Tex. Gov’t Code § 2253.044.

Sending the required notices on time is crucial for subcontractors but is often overlooked until it is too late or sent incorrectly due to a misunderstanding of the applicable laws. Subcontractors often wait too long believing that they will work something out with the general contractor. When they eventually do seek help from an attorney, the deadline has already passed. Subcontractors should pay careful attention to their past due invoices and ensure they seek an attorney’s advice far enough in advance so that all deadlines can be met and the subcontractor’s rights protected.

Texas law governing public projects can be found in Texas Government Code Chapter 2253 (formerly known as the McGregor Act) and Texas Property Code Chapter 53.

Please visit our blog again in a few days for Part 4: Public Works Construction Projects & Subcontractors: Prime Contracts Over $25,000.00 & Retainage.

Posted by Sarah F. Berry.

Friday, May 1, 2009

Part 2: Public Works Projects & Subcontractors ("First Tier Claimants"): Prime Contracts Less Than $25,000.00

As noted in Part 1 of the series, in most cases, subcontractors ("First Tier Claimants") on public projects who have not been paid by the general contractor may make a claim on the payment bond posted by the general contractor. However, when the general contractor’s contract with the public entity is less than $25,000.00, the general contractor is not required to post a payment bond. Consequently, when the contract is less than $25,000.00, subcontractors have limited lien rights. The lien attaches to money due to the general contractor. (Tex. Prop. Code § 53.231).
To assert a lien, the subcontractor must give notice to both the general contractor and the appropriate public official. (Tex. Prop. Code § 53.232). Subcontractors must ensure that they strictly comply with notice deadlines and content requirements or they risk not perfecting their lien. The subcontractor must give the notice before any payment is made to the general contractor and not later than the 15th day of the 2nd month following the month in which the work was performed or the material furnished. (Tex. Prop. Code § 53.234). The notice must contain specific information relating to the labor performed or materials delivered. The notice must include (1) the amount claimed; (2) the name of the party to whom the materials were delivered or for whom the labor was performed; (3) the dates and place of delivery or performance; (4) a description reasonably sufficient to identify the materials delivered or labor performed and the amount due; (5) a description reasonably sufficient to identify the project for which the material was delivered or the labor performed; and (6) the claimant's business address. (Tex. Prop. Code § 53.233). The notice must also be accompanied by a sworn statement that the amount claimed is just and correct and that all payments, lawful offsets, and credits known to the affiant have been allowed. (Tex. Prop. Code § 53.233). Failure to comply with any of the notice requirements may result in loss of the lien.
When the public official receives notice, he should retain from the money due to the general contractor enough to pay the claim for which the notice was given. (Tex. Prop. Code § 53.233).
A general contractor may file a bond with the public entity to release the lien and obtain the money withheld. (Tex. Prop. Code § 53.236). The subcontractor must sue on the bond within 6 months after the bond is filed. (Tex. Prop. Code § 53.239).
Please visit our blog again in a few days for Part 3: Public Works Construction Projects & Subcontractors: Prime Contracts Over $25,000.00.

Texas law governing public projects can be found in Texas Government Code Chapter 2253 (formerly known as the McGregor Act) and Texas Property Code Chapter 53.

Posted by Sarah F. Berry.